View of the Entrance to 121 Broadway, rendering by BXP
121 Broadway is a high-rise residential project currently under construction and is slated for completion in 2027. The development is all electric and features 439 apartments. Of these units, 20% are designated as affordable and an additional 5% are reserved for middle-income households. The building will also include tenant amenities such as an indoor family room, a dog run, and a viewing platform on the top floor overlooking the Boston skyline. The ground plane includes a substantial retail area, a double-height lobby, and a shared public porch area with an integrated water feature.
BXP obtained a building permit for the project in early 2024, construction of its foundation began in spring 2025, and the building remains on target to be completed by summer, 2027.
Review and Approval Documents:
135 Broadway Design Book (Approved April 12, 2022)
IDCP Amendment II Master Plan (Approved January 14, 2022)
Massachusetts Environmental Policy Act - Certificate of Approval (November 2021)
This Project is Part of the IDCP (Infill Development Concept Plan). See other projects:
-
Project Partners:
BXP
Architect:
Stantec
Landscape Architect:
Lemon Brooke
General Contractor:
Truner Constructon
Year Started:
2019 -
Joel Smith, ext 14, jsmith@cambridgeredevelopment.org